Dawn

Schedule R11

exported 2026-05-07
Tasks
99
In progress
9
Not started
89
Ask AI about your schedule Opens a new chat with your data already linked — no copying or uploading needed.
# Task Deps Dur Start Finish Res Status
1 Structural demolition and framing 214d 2025-06-01 06-01
9 Structural concrete / site final grade 47d 2026-06-01 06-01 2026-07-25 07-25 WMB Not Started
10 WATERPROOFING
11 Exterior waterproof deck part 2 14d 2026-07-03 07-03 2026-07-18 07-18 WMB Not Started
12 Exterior waterproof stucco AFTER WINDOWS 5d 2026-05-15 05-15 2026-05-20 05-20 WMB In Progress
13 EXTERIORS 216d 2025-12-05 12-05 2026-08-21 08-21 WMB In Progress
14 Exterior Door/ Window/ install/ upper floor/glass 6d 2026-05-08 05-08 2026-05-14 05-14 WMB In Progress
16 Install replacement window C 4d 2026-05-11 05-11 2026-05-14 05-14 JFC Not Started
19 Exterior Metal Break/ shop drawing / prepare 2d 2026-05-12 05-12 2026-05-13 05-13 SUB Not Started
20 Exterior Metal Break/ shop drawing / review approve 5d 2026-05-14 05-14 2026-05-19 05-19 MCP Not Started
21 Exterior Metal Break/ fabricate 10d 2026-05-21 05-21 2026-06-02 06-02 MCP Not Started
22 Exterior Metal Break/ install 1d 2026-06-03 06-03 2026-06-03 06-03 Not Started
25 Exterior Trellis/ Equipment/ select/ fabricate 60d 2026-04-26 04-26 2026-07-06 07-06 SUB Not Started
26 Exterior Trellis / install 8" perimeter tubing in trellis wells and flange 41d 2026-06-26 06-26 2026-08-12 08-12 SUB In Progress
27 Exterior Trellis / fabricate and install trellis pergola infill panels 8d 2026-08-13 08-13 2026-08-21 08-21 SUB Not Started
28 Exterior Trellis/ fabricate and install cladding 8d 2026-08-13 08-13 2026-08-21 08-21 SUB Not Started
29 Exterior Pool/ Equipment/ select/ prepare 7d 2026-05-15 05-15 2026-05-22 05-22 WMB Not Started
30 Exterior Pool/ Equipment / select/ review 7d 2026-05-23 05-23 2026-06-01 06-01 WMB Not Started
31 Exterior Pool/ Equipment/ select/ approve 14d 2026-03-20 03-20 2026-04-04 04-04 MCP Not Started
32 Exterior Pool/ Equipment/ order 28d 2026-04-06 04-06 2026-05-07 05-07 WMB Not Started
33 Exterior Pool/ Equipment/ install 20d 2026-05-08 05-08 2026-06-01 06-01 WMB Not Started
38 Exterior Deck/ Tile/ install 18d 2026-07-03 07-03 2026-07-23 07-23 WMB Not Started
39 Exterior Pool/ Tile/ install 10d 2026-07-24 07-24 2026-08-04 08-04 WMB Not Started
41 Exterior Pool/ plaster/ select/ review 30d 2026-05-13 05-13 2026-06-17 06-17 MCP Not Started
42 Exterior Pool/ plaster/ select/ approve 5d 2026-06-18 06-18 2026-06-24 06-24 MCP Not Started
43 Exterior Pool/ plaster/ order 1d 2026-06-25 06-25 2026-06-25 06-25 WMB Not Started
44 Exterior Pool/ plaster / install 1d 2026-08-05 08-05 2026-08-05 08-05 WMB Not Started
45 Exterior Pool/ cover/ select/ prepare 10d 2026-05-13 05-13 2026-05-23 05-23 MCP Not Started
46 Exterior Pool/ cover/ select/ review 7d 2026-05-26 05-26 2026-06-02 06-02 WMB Not Started
47 Exterior Pool/ cover/ select/ approve 7d 2026-06-03 06-03 2026-06-10 06-10 WMB Not Started
48 Exterior Pool/ cover/ order 7d 2026-06-11 06-11 2026-06-18 06-18 SUB Not Started
49 Exterior Pool/ cover/ install 1d 2026-08-06 08-06 2026-08-06 08-06 SUB Not Started
50 STUCCO 78d 2026-04-01 04-01 2026-07-02 07-02 Not Started
53 Exterior Stucco/ additional dryrot was found/ demo 30d 2026-04-01 04-01 2026-05-05 05-05 SUB In Progress
54 Exterior Stucco/ additional dryrot was found/ repair dryrot areas 8d 2026-05-06 05-06 2026-05-14 05-14 WMB Not Started
55 Exterior Stucco / install vapor barrier and wire for stucco 10d 2026-05-15 05-15 2026-05-27 05-27 SUB Not Started
56 Exterior Stucco/ Inspection for vapor barrier and wire 5d 2026-05-28 05-28 2026-06-02 06-02 SUB Not Started
57 Exterior Stucco/ Scratch coat for stucco 5d 2026-06-03 06-03 2026-06-08 06-08 SUB Not Started
58 Exterior Stucco /Brown coat installation 10d 2026-06-09 06-09 2026-06-20 06-20 SUB Not Started
59 Exterior Stucco/ Finish coat 10d 2026-06-22 06-22 2026-07-02 07-02 SUB Not Started
60 GLASS RAILINGS 206d 2025-12-08 12-08 2026-08-12 08-12 Not Started
67 Exterior Glass/ angle base shoe bracket lower deck 30d 2026-04-29 04-29 2026-06-03 06-03 SUB In Progress
68 Exterior Glass/ angle base shoe bracket main deck 30d 2026-06-04 06-04 2026-07-09 07-09 SUB Not Started
69 Exterior Glass/ measure for glass and cladding 10d 2026-06-23 06-23 2026-07-03 07-03 SUB Not Started
70 Exterior Glass/ order glass 10d 2026-07-04 07-04 2026-07-15 07-15 SUB Not Started
71 Exterior Glass/ install glass and cap rail 5d 2026-08-07 08-07 2026-08-12 08-12 SUB Not Started
72 SYSTEMS Rough ins 79d 2026-02-27 02-27 2026-05-30 05-30 Not Started
75 Rough HVAC lines EXCPET FOR ONE REGISTER 45d 2026-03-28 03-28 2026-05-19 05-19 SUB Not Started
76 Rough HVAC supply and return / gym, master bedroom / vent locations 18d 2026-04-24 04-24 2026-05-14 05-14 MCP In Progress
77 Rough HVAC supply and return /gym, master bedroom / vent 7d 2026-05-09 05-09 2026-05-16 05-16 SUB Not Started
80 Window and Door Shades / change order / submitt 5d 2026-04-17 04-17 2026-04-22 04-22 SUB In Progress
81 Window and Door Shades / change order / approval 20d 2026-04-23 04-23 2026-05-15 05-15 MCP In Progress
82 Window and Door Shades / rough in / electrical 5d 2026-05-16 05-16 2026-05-21 05-21 SUB Not Started
83 Window and Door Shades / pocket order 10d 2026-05-16 05-16 2026-05-28 05-28 SUB Not Started
84 Window and Door Shades / install 2d 2026-05-29 05-29 2026-05-30 05-30 WMB Not Started
85 Rough inspection 1d 2026-05-08 05-08 2026-05-08 05-08 WMB Not Started
86 Correction buffer 2d 2026-05-09 05-09 2026-05-11 05-11 WMB Not Started
87 Close inspection 5d 2026-05-12 05-12 2026-05-16 05-16 WMB Not Started
88 INTERIORS 182d 2025-12-12 12-12 2026-07-20 07-20 WMB Not Started
94 Interior Tile Backer/ order 1d 2026-05-18 05-18 2026-05-18 05-18 WMB Not Started
95 Interior Tile Backer/ install 3d 2026-05-19 05-19 2026-05-21 05-21 WMB Not Started
96 Interior Tile Backer/ inspect 1d 2026-05-22 05-22 2026-05-22 05-22 BLDG Not Started
97 Interior Tile Backer/ Waterproof 3d 2026-05-23 05-23 2026-05-27 05-27 WMB Not Started
98 Interior tile bahtroom shower wall 10d 2026-05-28 05-28 2026-06-08 06-08 WMB Not Started
99 Interior tile bathroom floor 5d 2026-06-09 06-09 2026-06-13 06-13 WMB Not Started
100 Interior Insulation, baseboard, drywall/ data sheet/ prepared 5d 2026-05-05 05-05 2026-05-11 05-11 MCP Not Started
101 Interior Insulation, baseboard, drywall/ data sheet review 1d 2026-05-12 05-12 2026-05-12 05-12 WMB Not Started
102 Interior Insulation, baseboard, drywall/ data sheet/ approve 2d 2026-05-12 05-12 2026-05-13 05-13 MCP Not Started
103 Interior Insulation/ insulation order 5d 2026-05-14 05-14 2026-05-19 05-19 SUB Not Started
104 Interior Insulation/ installation 10d 2026-05-14 05-14 2026-05-29 05-29 SUB Not Started
105 Interior Baseboard/ order 2d 2026-05-14 05-14 2026-05-15 05-15 WMB Not Started
106 Interior Baseboard/ installation 4d 2026-05-16 05-16 2026-05-19 05-19 WMB Not Started
107 Interior Sheetrock/ order 5d 2026-05-14 05-14 2026-05-19 05-19 SUB Not Started
108 Interior Sheetrock/ install 10d 2026-05-21 05-21 2026-06-02 06-02 SUB Not Started
109 Interior Sheetrock/ screw inspection/ schedule 1d 2026-06-03 06-03 2026-06-03 06-03 BLDG Not Started
110 Interior Sheetrock/ mud, tape and sand 20d 2026-06-04 06-04 2026-06-27 06-27 SUB Not Started
111 Interior Shower glass/ selection/ data sheet/ prepared 5d 2026-05-13 05-13 2026-05-18 05-18 MCP Not Started
116 Interior Paint/ selection/ data sheet/ prepared 5d 2026-05-13 05-13 2026-05-18 05-18 WMB Not Started
117 Interior Paint/ selection/ review 5d 2026-05-19 05-19 2026-05-23 05-23 WMB Not Started
118 Interior Paint/ selection/ approve 5d 2026-05-26 05-26 2026-05-30 05-30 MCP Not Started
119 Interior Paint/ order material 7d 2026-05-26 05-26 2026-06-03 06-03 SUB Not Started
120 Interior Prime/ application 3d 2026-06-29 06-29 2026-07-01 07-01 SUB Not Started
121 Interior Paint/ application/ two 10d 2026-07-06 07-06 2026-07-16 07-16 WMB Not Started
122 Interior Paint/ touch up 3d 2026-07-17 07-17 2026-07-20 07-20 WMB Not Started
123 Interior Closet/ Vanity/ selection/ data sheet/ prepared 15d 2026-05-13 05-13 2026-06-03 06-03 SUB Not Started
124 Interior Vanity Closet/ selection/ data sheet/ review 5d 2026-05-29 05-29 2026-06-03 06-03 WMB Not Started
125 Interior Vanity Closet / selection/ data sheet/ approved 5d 2026-06-04 06-04 2026-06-09 06-09 MCP Not Started
126 Interior Vanity Closet/ order 30d 2026-06-10 06-10 2026-07-15 07-15 WMB Not Started
127 Interior Vanity Closet/ install 3d 2026-07-02 07-02 2026-07-04 07-04 WMB Not Started
133 Interior Doors/ install 30d 2026-04-11 04-11 2026-05-15 05-15 WMB In Progress
134 Interior Door hardware/ selection/ data sheet/ prepared 10d 2026-05-13 05-13 2026-05-23 05-23 MCP Not Started
135 Interior Door hardware selection/ data sheet/ review 5d 2026-05-26 05-26 2026-05-30 05-30 WMB Not Started
136 Interior Door hardware/ selection/ data sheet/ approved 5d 2026-06-01 06-01 2026-06-05 06-05 MCP Not Started
137 Interior Door hardware/ pcoket door order 30d 2026-06-06 06-06 2026-07-11 07-11 WMB Not Started
139 Interior Door hardware/ install 1d 2026-07-17 07-17 2026-07-17 07-17 WMB Not Started
140 SYSTEMS TRIM OUT 9d 2026-07-06 07-06 2026-07-15 07-15 WMB Not Started
141 System trim out/ plumbing 3d 2026-07-06 07-06 2026-07-08 07-08 SUB Not Started
142 System trim out/ HVAC 6d 2026-07-06 07-06 2026-07-11 07-11 SUB Not Started
143 System trim out/ electrical 7d 2026-07-06 07-06 2026-07-13 07-13 SUB Not Started
144 System trim out/ fire protection 7d 2026-07-06 07-06 2026-07-13 07-13 SUB Not Started
145 System trim out/ window shades 7d 2026-07-06 07-06 2026-07-13 07-13 SUB Not Started
146 2nd coat of interior paint 2d 2026-07-14 07-14 2026-07-15 07-15 SUB Not Started
147 CLOSE OUT 36d 2026-07-16 07-16 2026-08-26 08-26 WMB Not Started
148 Restore exterior area 7d 2026-08-13 08-13 2026-08-20 08-20 WMB Not Started
149 Final inspection 1d 2026-07-16 07-16 2026-07-16 07-16 BLDG Not Started
150 Final clean up 2d 2026-08-07 08-07 2026-08-08 08-08 WMB Not Started
151 Punch list 5d 2026-08-21 08-21 2026-08-26 08-26 WMB Not Started