Exterior Metal Break/ shop drawing / review approve
Current — R11
- Start
- 2026-05-14
- Finish
- 2026-05-19
- Duration
- 5 days
- Resource
- MCP
- GC row
- #20
Predecessors
Successors
None.
Timeline across revisions
| Rev | Exported | Start | Finish | Dur | Status |
|---|---|---|---|---|---|
| R11 | 2026-04-17 | 2026-04-29 | 2026-05-04 | 5d | Not Started |
| R11 | 2026-05-07 | 2026-05-14 Δ | 2026-05-19 Δ | 5d | Not Started |