Changes
Date moved (90)
| Task | Phase | Start | Finish |
|---|---|---|---|
| Exterior Trellis/ Equipment/ select/ fabricate | EXTERIORS |
2025-12-22
→
2026-04-26
+125d
|
2026-03-06
→
2026-07-06
+122d
|
| Exterior Pool/ plaster/ order | EXTERIORS |
2026-04-29
→
2026-06-25
+57d
|
2026-04-29
→
2026-06-25
+57d
|
| Exterior Pool/ plaster/ select/ approve | EXTERIORS |
2026-04-23
→
2026-06-18
+56d
|
2026-04-28
→
2026-06-24
+57d
|
| Exterior Pool/ plaster/ select/ review | EXTERIORS |
2026-03-19
→
2026-05-13
+55d
|
2026-04-22
→
2026-06-17
+56d
|
| Exterior Glass/ angle base shoe bracket lower deck | GLASS RAILINGS |
2026-04-11
→
2026-04-29
+18d
|
2026-04-28
→
2026-06-03
+36d
|
| Exterior Glass/ angle base shoe bracket main deck | GLASS RAILINGS |
2026-04-29
→
2026-06-04
+36d
|
2026-06-03
→
2026-07-09
+36d
|
| Interior Doors/ install | INTERIORS |
2026-03-11
→
2026-04-11
+31d
|
2026-05-01
→
2026-05-15
+14d
|
| Exterior Pool/ Equipment / select/ review | EXTERIORS |
2026-05-02
→
2026-05-23
+21d
|
2026-05-09
→
2026-06-01
+23d
|
| Interior Closet/ Vanity/ selection/ data sheet/ prepared | INTERIORS |
2026-04-24
→
2026-05-13
+19d
|
2026-05-11
→
2026-06-03
+23d
|
| Window and Door Shades / install | SYSTEMS Rough ins |
2026-05-07
→
2026-05-29
+22d
|
2026-05-08
→
2026-05-30
+22d
|
| Window and Door Shades / pocket order | SYSTEMS Rough ins |
2026-04-25
→
2026-05-16
+21d
|
2026-05-06
→
2026-05-28
+22d
|
| Exterior Pool/ Equipment/ select/ prepare | EXTERIORS |
2026-04-24
→
2026-05-15
+21d
|
2026-05-01
→
2026-05-22
+21d
|
| Window and Door Shades / change order / approval | SYSTEMS Rough ins | 2026-04-23 |
2026-04-24
→
2026-05-15
+21d
|
| Window and Door Shades / rough in / electrical | SYSTEMS Rough ins |
2026-04-25
→
2026-05-16
+21d
|
2026-04-30
→
2026-05-21
+21d
|
| Exterior Pool/ cover/ order | EXTERIORS |
2026-05-22
→
2026-06-11
+20d
|
2026-05-30
→
2026-06-18
+19d
|
| Exterior Pool/ cover/ select/ approve | EXTERIORS |
2026-05-14
→
2026-06-03
+20d
|
2026-05-21
→
2026-06-10
+20d
|
| Exterior Pool/ cover/ select/ review | EXTERIORS |
2026-05-06
→
2026-05-26
+20d
|
2026-05-13
→
2026-06-02
+20d
|
| Interior Door hardware/ selection/ data sheet/ approved | INTERIORS |
2026-05-12
→
2026-06-01
+20d
|
2026-05-16
→
2026-06-05
+20d
|
| Interior Door hardware selection/ data sheet/ review | INTERIORS |
2026-05-06
→
2026-05-26
+20d
|
2026-05-11
→
2026-05-30
+19d
|
| Interior Paint/ selection/ approve | INTERIORS |
2026-05-06
→
2026-05-26
+20d
|
2026-05-11
→
2026-05-30
+19d
|
| Exterior Pool/ cover/ select/ prepare | EXTERIORS |
2026-04-24
→
2026-05-13
+19d
|
2026-05-05
→
2026-05-23
+18d
|
| Exterior Glass/ measure for glass and cladding | GLASS RAILINGS |
2026-06-04
→
2026-06-23
+19d
|
2026-06-15
→
2026-07-03
+18d
|
| Interior Door hardware/ pcoket door order | INTERIORS |
2026-05-18
→
2026-06-06
+19d
|
2026-06-23
→
2026-07-11
+18d
|
| Interior Door hardware/ selection/ data sheet/ prepared | INTERIORS |
2026-04-24
→
2026-05-13
+19d
|
2026-05-05
→
2026-05-23
+18d
|
| Interior Paint/ selection/ data sheet/ prepared | INTERIORS |
2026-04-24
→
2026-05-13
+19d
|
2026-04-29
→
2026-05-18
+19d
|
| Interior Paint/ selection/ review | INTERIORS |
2026-04-30
→
2026-05-19
+19d
|
2026-05-05
→
2026-05-23
+18d
|
| Interior Shower glass/ selection/ data sheet/ prepared | INTERIORS |
2026-04-24
→
2026-05-13
+19d
|
2026-04-29
→
2026-05-18
+19d
|
| Exterior Stucco /Brown coat installation | STUCCO |
2026-05-21
→
2026-06-09
+19d
|
2026-06-02
→
2026-06-20
+18d
|
| Exterior Stucco/ Finish coat | STUCCO |
2026-06-03
→
2026-06-22
+19d
|
2026-06-13
→
2026-07-02
+19d
|
| Exterior Stucco/ Inspection for vapor barrier and wire | STUCCO |
2026-05-09
→
2026-05-28
+19d
|
2026-05-14
→
2026-06-02
+19d
|
| Exterior Stucco / install vapor barrier and wire for stucco | STUCCO |
2026-05-04
→
2026-05-15
+11d
|
2026-05-08
→
2026-05-27
+19d
|
| Exterior Stucco/ Scratch coat for stucco | STUCCO |
2026-05-15
→
2026-06-03
+19d
|
2026-05-20
→
2026-06-08
+19d
|
| Exterior Deck/ Tile/ install | EXTERIORS |
2026-06-15
→
2026-07-03
+18d
|
2026-07-06
→
2026-07-23
+17d
|
| Exterior Pool/ plaster / install | EXTERIORS |
2026-07-18
→
2026-08-05
+18d
|
2026-07-18
→
2026-08-05
+18d
|
| Exterior Pool/ Tile/ install | EXTERIORS |
2026-07-07
→
2026-07-24
+17d
|
2026-07-17
→
2026-08-04
+18d
|
| Exterior Glass/ order glass | GLASS RAILINGS |
2026-06-16
→
2026-07-04
+18d
|
2026-06-27
→
2026-07-15
+18d
|
| Interior Vanity Closet/ order | INTERIORS |
2026-05-23
→
2026-06-10
+18d
|
2026-06-29
→
2026-07-15
+16d
|
| Interior Vanity Closet / selection/ data sheet/ approved | INTERIORS |
2026-05-18
→
2026-06-04
+17d
|
2026-05-22
→
2026-06-09
+18d
|
| Interior Vanity Closet/ selection/ data sheet/ review | INTERIORS |
2026-05-12
→
2026-05-29
+17d
|
2026-05-16
→
2026-06-03
+18d
|
| Exterior waterproof deck part 2 | WATERPROOFING |
2026-06-15
→
2026-07-03
+18d
|
2026-07-01
→
2026-07-18
+17d
|
| Final clean up | CLOSE OUT |
2026-07-21
→
2026-08-07
+17d
|
2026-07-22
→
2026-08-08
+17d
|
| Exterior Pool/ cover/ install | EXTERIORS |
2026-07-20
→
2026-08-06
+17d
|
2026-07-20
→
2026-08-06
+17d
|
| Exterior Glass/ install glass and cap rail | GLASS RAILINGS |
2026-07-21
→
2026-08-07
+17d
|
2026-07-31
→
2026-08-12
+12d
|
| Interior Insulation, baseboard, drywall/ data sheet/ prepared | INTERIORS |
2026-04-24
→
2026-05-05
+11d
|
2026-04-24
→
2026-05-11
+17d
|
| Interior Insulation, baseboard, drywall/ data sheet review | INTERIORS |
2026-04-25
→
2026-05-12
+17d
|
2026-04-25
→
2026-05-12
+17d
|
| Interior Prime/ application | INTERIORS |
2026-06-12
→
2026-06-29
+17d
|
2026-06-15
→
2026-07-01
+16d
|
| Interior Sheetrock/ install | INTERIORS |
2026-05-06
→
2026-05-21
+15d
|
2026-05-16
→
2026-06-02
+17d
|
| Interior Paint/ application/ two | INTERIORS |
2026-06-20
→
2026-07-06
+16d
|
2026-07-01
→
2026-07-16
+15d
|
| Interior Paint/ touch up | INTERIORS |
2026-07-02
→
2026-07-17
+15d
|
2026-07-04
→
2026-07-20
+16d
|
| Interior Sheetrock/ mud, tape and sand | INTERIORS |
2026-05-19
→
2026-06-04
+16d
|
2026-06-11
→
2026-06-27
+16d
|
| Interior Sheetrock/ screw inspection/ schedule | INTERIORS |
2026-05-18
→
2026-06-03
+16d
|
2026-05-18
→
2026-06-03
+16d
|
| Interior Vanity Closet/ install | INTERIORS |
2026-06-16
→
2026-07-02
+16d
|
2026-06-18
→
2026-07-04
+16d
|
| Rough inspection | SYSTEMS Rough ins |
2026-04-22
→
2026-05-08
+16d
|
2026-04-28
→
2026-05-08
+10d
|
| System trim out/ electrical | SYSTEMS TRIM OUT |
2026-06-20
→
2026-07-06
+16d
|
2026-06-27
→
2026-07-13
+16d
|
| System trim out/ fire protection | SYSTEMS TRIM OUT |
2026-06-20
→
2026-07-06
+16d
|
2026-06-27
→
2026-07-13
+16d
|
| System trim out/ HVAC | SYSTEMS TRIM OUT |
2026-06-20
→
2026-07-06
+16d
|
2026-06-26
→
2026-07-11
+15d
|
| System trim out/ plumbing | SYSTEMS TRIM OUT |
2026-06-20
→
2026-07-06
+16d
|
2026-06-23
→
2026-07-08
+15d
|
| System trim out/ window shades | SYSTEMS TRIM OUT |
2026-06-20
→
2026-07-06
+16d
|
2026-06-27
→
2026-07-13
+16d
|
| Final inspection | CLOSE OUT |
2026-07-01
→
2026-07-16
+15d
|
2026-07-01
→
2026-07-16
+15d
|
| Exterior Metal Break/ shop drawing / prepare | EXTERIORS |
2026-04-27
→
2026-05-12
+15d
|
2026-04-28
→
2026-05-13
+15d
|
| Exterior Metal Break/ shop drawing / review approve | EXTERIORS |
2026-04-29
→
2026-05-14
+15d
|
2026-05-04
→
2026-05-19
+15d
|
| Interior Baseboard/ installation | INTERIORS |
2026-05-01
→
2026-05-16
+15d
|
2026-05-05
→
2026-05-19
+14d
|
| Interior Baseboard/ order | INTERIORS |
2026-04-29
→
2026-05-14
+15d
|
2026-04-30
→
2026-05-15
+15d
|
| Interior Door hardware/ install | INTERIORS |
2026-07-02
→
2026-07-17
+15d
|
2026-07-02
→
2026-07-17
+15d
|
| Interior Insulation, baseboard, drywall/ data sheet/ approve | INTERIORS |
2026-04-27
→
2026-05-12
+15d
|
2026-04-28
→
2026-05-13
+15d
|
| Interior Insulation/ insulation order | INTERIORS |
2026-04-29
→
2026-05-14
+15d
|
2026-05-04
→
2026-05-19
+15d
|
| Interior Paint/ order material | INTERIORS |
2026-05-12
→
2026-05-26
+14d
|
2026-05-19
→
2026-06-03
+15d
|
| Interior Sheetrock/ order | INTERIORS |
2026-04-29
→
2026-05-14
+15d
|
2026-05-04
→
2026-05-19
+15d
|
| 2nd coat of interior paint | SYSTEMS TRIM OUT |
2026-06-29
→
2026-07-14
+15d
|
2026-06-30
→
2026-07-15
+15d
|
| Exterior Door/ Window/ install/ upper floor/glass | EXTERIORS |
2026-04-24
→
2026-05-08
+14d
|
2026-04-30
→
2026-05-14
+14d
|
| Install replacement window C | EXTERIORS |
2026-04-27
→
2026-05-11
+14d
|
2026-04-30
→
2026-05-14
+14d
|
| Exterior Metal Break/ fabricate | EXTERIORS |
2026-05-09
→
2026-05-21
+12d
|
2026-05-20
→
2026-06-02
+13d
|
| Exterior Metal Break/ install | EXTERIORS |
2026-05-21
→
2026-06-03
+13d
|
2026-05-21
→
2026-06-03
+13d
|
| Exterior Trellis / install 8" perimeter tubing in trellis wells and flange | EXTERIORS |
2026-06-13
→
2026-06-26
+13d
|
2026-07-31
→
2026-08-12
+12d
|
| Punch list | CLOSE OUT |
2026-08-10
→
2026-08-21
+11d
|
2026-08-14
→
2026-08-26
+12d
|
| Restore exterior area | CLOSE OUT |
2026-08-01
→
2026-08-13
+12d
|
2026-08-08
→
2026-08-20
+12d
|
| Exterior Trellis/ fabricate and install cladding | EXTERIORS |
2026-08-01
→
2026-08-13
+12d
|
2026-08-10
→
2026-08-21
+11d
|
| Exterior Trellis / fabricate and install trellis pergola infill panels | EXTERIORS |
2026-08-01
→
2026-08-13
+12d
|
2026-08-10
→
2026-08-21
+11d
|
| Exterior Stucco/ additional dryrot was found/ demo | STUCCO | 2026-04-01 |
2026-04-23
→
2026-05-05
+12d
|
| Exterior Stucco/ additional dryrot was found/ repair dryrot areas | STUCCO |
2026-04-24
→
2026-05-06
+12d
|
2026-05-02
→
2026-05-14
+12d
|
| Exterior waterproof stucco AFTER WINDOWS | WATERPROOFING |
2026-05-04
→
2026-05-15
+11d
|
2026-05-08
→
2026-05-20
+12d
|
| Close inspection | SYSTEMS Rough ins |
2026-05-02
→
2026-05-12
+10d
|
2026-05-08
→
2026-05-16
+8d
|
| Correction buffer | SYSTEMS Rough ins |
2026-04-29
→
2026-05-09
+10d
|
2026-05-01
→
2026-05-11
+10d
|
| Interior Insulation/ installation | INTERIORS |
2026-05-09
→
2026-05-14
+5d
|
2026-05-20
→
2026-05-29
+9d
|
| Interior Tile Backer/ order | INTERIORS |
2026-05-09
→
2026-05-18
+9d
|
2026-05-09
→
2026-05-18
+9d
|
| Interior Tile Backer/ Waterproof | INTERIORS |
2026-05-15
→
2026-05-23
+8d
|
2026-05-18
→
2026-05-27
+9d
|
| Interior tile bahtroom shower wall | INTERIORS |
2026-05-19
→
2026-05-28
+9d
|
2026-05-30
→
2026-06-08
+9d
|
| Interior Tile Backer/ inspect | INTERIORS |
2026-05-14
→
2026-05-22
+8d
|
2026-05-14
→
2026-05-22
+8d
|
| Interior Tile Backer/ install | INTERIORS |
2026-05-11
→
2026-05-19
+8d
|
2026-05-13
→
2026-05-21
+8d
|
| Interior tile bathroom floor | INTERIORS |
2026-06-01
→
2026-06-09
+8d
|
2026-06-05
→
2026-06-13
+8d
|
New tasks (3)
| Task | Phase | Start | Finish |
|---|---|---|---|
| Rough HVAC lines EXCPET FOR ONE REGISTER | SYSTEMS Rough ins | 2026-03-28 | 2026-05-19 |
| Rough HVAC supply and return / gym, master bedroom / vent locations | SYSTEMS Rough ins | 2026-04-24 | 2026-05-14 |
| Rough HVAC supply and return /gym, master bedroom / vent | SYSTEMS Rough ins | 2026-05-09 | 2026-05-16 |
Removed tasks (9)
| Task | Phase | Start | Finish |
|---|---|---|---|
| Deliver replacement window C | EXTERIORS | 2026-04-24 | 2026-04-25 |
| Exterior Pool & Deck/ Tile/ order | EXTERIORS | 2026-01-29 | 2026-03-05 |
| Exterior Stucco/ data sheet/ prepared | STUCCO | 2026-04-01 | 2026-04-23 |
| Exterior Stucco/ shop drawings / review | STUCCO | 2026-04-24 | 2026-04-29 |
| HVAC Engineering information / Rev Elecrtircal layout | SYSTEMS Rough ins | 2026-02-27 | 2026-03-27 |
| Rough HVAC | SYSTEMS Rough ins | 2026-03-28 | 2026-04-13 |
| Rough electrical | SYSTEMS Rough ins | 2026-03-28 | 2026-04-17 |
| Rough fire sprinklers | SYSTEMS Rough ins | 2026-04-18 | 2026-04-21 |
| Rough plumbing | SYSTEMS Rough ins | 2026-03-20 | 2026-04-06 |