Exterior Glass/ measure for glass and cladding
Current — R11
- Start
- 2026-06-23
- Finish
- 2026-07-03
- Duration
- 10 days
- Resource
- SUB
- GC row
- #69
Predecessors
Successors
None.
Timeline across revisions
| Rev | Exported | Start | Finish | Dur | Status |
|---|---|---|---|---|---|
| R11 | 2026-04-17 | 2026-06-04 | 2026-06-15 | 10d | Not Started |
| R11 | 2026-05-07 | 2026-06-23 Δ | 2026-07-03 Δ | 10d | Not Started |