Exterior Stucco/ Inspection for vapor barrier and wire
Current — R11
- Start
- 2026-05-28
- Finish
- 2026-06-02
- Duration
- 5 days
- Resource
- SUB
- GC row
- #56
Predecessors
Successors
Timeline across revisions
| Rev | Exported | Start | Finish | Dur | Status |
|---|---|---|---|---|---|
| R11 | 2026-04-17 | 2026-05-09 | 2026-05-14 | 5d | Not Started |
| R11 | 2026-05-07 | 2026-05-28 Δ | 2026-06-02 Δ | 5d | Not Started |