Exterior Stucco / install vapor barrier and wire for stucco
Current — R11
- Start
- 2026-05-15
- Finish
- 2026-05-27
- Duration
- 10 days
- Resource
- SUB
- GC row
- #55
Predecessors
Successors
Timeline across revisions
| Rev | Exported | Start | Finish | Dur | Status |
|---|---|---|---|---|---|
| R11 | 2026-04-17 | 2026-05-04 | 2026-05-08 | 5d | Not Started |
| R11 | 2026-05-07 | 2026-05-15 Δ | 2026-05-27 Δ | 10d | Not Started |