Exterior Trellis / install 8" perimeter tubing in trellis wells and flange
Current — R11
- Start
- 2026-06-26
- Finish
- 2026-08-12
- Duration
- 41 days
- Resource
- SUB
- GC row
- #26
Predecessors
Successors
None.
Timeline across revisions
| Rev | Exported | Start | Finish | Dur | Status |
|---|---|---|---|---|---|
| R11 | 2026-04-17 | 2026-06-13 | 2026-07-31 | 41d | In Progress |
| R11 | 2026-05-07 | 2026-06-26 Δ | 2026-08-12 Δ | 41d | In Progress |