HVAC Engineering information / Rev Elecrtircal layout
Current — R11
- Start
- 2026-02-27
- Finish
- 2026-03-27
- Duration
- 25 days
- Resource
- MCP
- GC row
- #74
Predecessors
None.
Successors
- Rough electrical · FS
- Rough HVAC · FS
Timeline across revisions
Only 1 revision ingested so far. Once a new weekly PDF lands, this table will show how dates and duration drift over time.
| Rev | Exported | Start | Finish | Dur | Status |
|---|---|---|---|---|---|
| R11 | 2026-04-17 | 2026-02-27 | 2026-03-27 | 25d | In Progress |