Rough fire sprinklers
Current — R11
- Start
- 2026-04-18
- Finish
- 2026-04-21
- Duration
- 3 days
- Resource
- SUB
- GC row
- #77
Predecessors
- Rough electrical · FS
Successors
- Rough inspection · FS
Timeline across revisions
Only 1 revision ingested so far. Once a new weekly PDF lands, this table will show how dates and duration drift over time.
| Rev | Exported | Start | Finish | Dur | Status |
|---|---|---|---|---|---|
| R11 | 2026-04-17 | 2026-04-18 | 2026-04-21 | 3d | Not Started |